What does it mean to cease the supply?

If a transfer cannot be agreed, which is Council's preferred option, Council could seek to cease the drinking water supply to Pourerere Beach Campground.

To cease the supply Council would have to undertake a formal statutory process, including at least 30 days notice under Taumata Arowai requirements.

However, camping grounds must have a potable (safe and suitable for drinking) water supply, the campground would not be able to continue operating unless the operator put an alternative compliant water source in place.

How much is it estimated to cost?

This is estimated to cost about $25,000 in process costs.

What are the pros of doing this?

  • Has the equal lowest whole-of-life cost for Council, estimated to be about $25,000 one-off cost to cover technical assessment, legal process and consultation.
  • Provides a clear long-term position.

What are the cons of doing this?

  • The campground could not continue operating in its current form unless the operator found an alternative compliant water source.
  • Requires a statutory process, consultation and further Council decisions before it can be put into effect.