What does it mean to transfer the supply?

The responsibility for managing the drinking water supply would be transferred from Central Hawke's Bay District Council to Pourerere Beach Camp Limited - a private company that leases the campground from Council.

Transferring responsibility for the supply would be a staged statutory process under the Local Government (Water Services) Act 2025.

Pourerere Beach Camp Limited would become responsible for providing safe drinking water to the campground, including meeting all compliance requirements and covering the associated costs and risks.

A number of matters would need to be worked through as part of a transfer, including:

  • Ownership of, and responsibility for, the existing assets (such as pipework and tanks)
  • Ongoing access to water sources
  • What happens to any informal connections upstream of the campground tanks
  • Any changes needed to the campground lease

For the transfer to happen, Council would need to undertake a number of legislative steps to do this, including notifying Taumata Arowai and the Medical Officer of Health, and holding a referendum with those affected by the transfer.

How much is it estimated to cost?

This is estimated to cost about $25,000 in process costs.

What are the pros of transferring the supply?

  • Has the equal lowest whole-of-life cost for Council, estimated about $25,000 one-off cost to cover technical assessment, legal process and consultation.
  • Provides a clear long-term position.
  • Fully removes the public health risk associated with any potential informal connections.
  • Is the only option likely to be manageable within Council’s current planning assumptions

What are the cons of doing this?

  • The campground operator takes on the cost of compliance, which may mean they have to increase site fees, which in turn may affect the campground’s viability.
  • Properties with informal connections would lose access to water, which may not meet community expectations.
  • Requires a statutory process, consultation and further Council decisions before it can be put into effect - which means it wouldn't be a short process.